Phase 1 begins in May 2022 and is expected to conclude by Fall 2022.
Show All Answers
Phase 1 will close John Street.
Below is the project map.
There will be no detours for the John St. closure. John St. will be open to residents and emergency service vehicles only.
The contractor, J.F. Wilkerson, will be providing all traffic control devices.
Possible residential driveway access could be impacted as well as utilities. If necessary, the contractor and Town representatives will communicate directly with those impacted.
Yes. John St. residents are excluded from the closure.
Yes. Emergency service vehicles are excluded from the closure.
J.F. Wilkerson.
If you have a question or concern, please contact the following Town Staff:
Shannon Poole - Construction Project Administrator
spoole@townofclaytonnc.org
Louis Duffie - Project Manager
lduffie@townofclaytonnc.org